Productivity and efficiency calculation

Productivity calculation

Most of the industrial engineers calculate worker/line efficiency on the basis of SAM value and actual productivity (per hour productivity of a operator/line). Below are the simple methods to calculate worker/line efficiency and productivity.

​Worker/line efficiency

SAM (Standard allowed minutes) of the garment = 10

Minutes produced by each labor =(40 pieces X 10) = 400 minutes

Minutes Available = 10 Hrs x 60 Minutest = 600

Worker/line efficiency = (Minutes Produced / Minutes Available) = (400/600*100)% = 66.66

Productivity per worker

Total production in day per line =1600 pieces

Total manpower (operator +helpers+ others) = 40

Working time = 600 minutes (10 hours)

Productivity for 10 hours is =Total pieces produced/ manpower = (1600/40) Pieces =40 pieces.

Prakash Dutt

Prakash Dutt

Prakash is a solid apparel professional with a broad experience in apparel manufacturing, sourcing, quality management, sustainability, and corporate social responsibility. He is a lean management professional (lean six sigma black belt), innovative and open to trying the opportunity for new technology and changes in the industry.

You may also like...

Leave a Reply

Your email address will not be published. Required fields are marked *